Shed Restoration at Grace Lutheran Church: Wednesday, November 25

On Wednesday, November 25, 2026, Geoffrey Dann N3CFX and Pedro Morillas K6MIL returned to Grace Lutheran Church, 6190 Telephone Road, Ventura, to continue the shed restoration. Saturday’s start is described in Shed Restoration at Grace Lutheran Church. Tuesday’s work, when the long walkway wall was primed and the old door was removed from the east wall, is described in Shed Restoration Update at Grace Lutheran Church.

Wednesday’s work focused on the east wall. Using the corner brackets and hinge set from a Peak gate kit, plus 2×4 lumber, they assembled the 2×4 structure of the new door and hung it in the east-wall opening, which took a lot of adjusting. They then attached exterior plywood to that structure, extending it above the 2x4s to match the height of the adjacent wall panel, and added metal flashing to the bottom of the door. The door was temporarily secured closed. Geoffrey Dann N3CFX and Pedro Morillas K6MIL took the photographs. Burt Rapp, who was on campus repairing rain gutters, stopped by the shed briefly.

They also made a trip to Lowe’s for another 2x4x8 for the door structure, a bundle of 1x3x8 for trim, a bundle of small wood shims, and three pieces of metal flashing. A church member donated the primer and green paint, which they left in the shed.

Work on the east wall continues. Still to do:

  • Remove the old trim from the remaining section of the wall, and install new exterior plywood and metal flashing there.
  • Trim a strip of plywood to fit next to the hinges.
  • Install an electrical outlet, a hasp or other lock, a threshold below the door, and trim around the door.
  • Possibly add 2×2 lumber on the top and hinge side of the door structure to match the non-hinge side, as Geoffrey noted.

Pedro suggested priming the new panels on the ground with a roller and a brush, rather than spraying them after installation. He also advised spraying only the inside, while wearing proper head and eye protection and a respirator.

When the shed is finished and painted to match the church’s other buildings, the club will use it to store picnic and Field Day supplies, so the gear no longer has to be kept at members’ homes.

Our sincere thanks again to Grace Lutheran Church for allowing the club to rebuild the shed and share it with them.

The back of a Peak gate kit box, with installation diagrams, resting on a plywood work table.
The Peak gate kit used for the door’s corner brackets and hinges, set out on the work table at the start of the day.
The front of a Peak gate kit box, showing a finished wooden gate with metal corner brackets.
The Peak gate kit used to assemble the east-wall door.
The east wall of the shed, with the new 2x4 door structure in the opening, looking into the shed.
The east wall of the shed, with the new 2×4 door structure in place in the opening where the old door had been.
Pedro Morillas K6MIL using a circular saw to cut a sheet of exterior plywood on a work table, with the shed in the background.
Pedro Morillas K6MIL measures and cuts a sheet of exterior plywood for the east-wall door.
The east wall of the shed at the end of the day, with new plywood on the door, temporarily braced closed, and a wooden ramp in front.
The east wall at the end of the November 25 work day. Exterior plywood has been attached to the door, extending to the same level as the adjacent wall panel, metal flashing has been installed at the bottom of the door, and the door has been temporarily secured closed.
A closer view of the east wall of the shed, with the new plywood door temporarily braced closed and a wooden ramp in front.
A closer view of the east wall at the end of the November 25 work day, with the new plywood door temporarily braced closed.
A close view of metal flashing along the bottom of the new plywood door, above a wooden ramp.
Metal flashing installed at the bottom of the new east-wall door.

Photos by Geoffrey Dann N3CFX and Pedro Morillas K6MIL

Bookmark the permalink.

Comments are closed.